4 May - start of surface replacement on the motorway A4 Katowice-Krakow

20 04 2016 #New

Please be informed that on 4 May works connected with surface replacement will start on the carriageway to Katowice between toll collection plaza in Balice and Rudno Jucntion on the section of 4 km (from km 386 to km 390). There will be a speed limit to 80 km/h.

Still there will be two lanes in each direction during the replacement works.On the carriageway to Katowice one lane will be opened and on the carriageway to Krakow there will be two lanes in Krakow direction and one lane in Katowice direction.

On 11 June replacement works will start on the carriageway to Krakow.

Replacement works between toll plaza in Balice and Rudno Junction are to be completed till 22 July and after the World Youth Day in Krakow replacement works will start on the section between junctions: Jelen and Balin.